Western Mental Health Institute

CASE STUDY

Western Mental Health Institute

Western Mental Health Institute partnered with Kitchens To Go for a swift, cost-effective modular kitchen solution, ensuring uninterrupted patient care.

Client

Western Mental Health Institute in Bolivar, TN

The Need

Urgent Kitchen Facility Replacement

The Solution

Innovative Modular Kitchen Transition

Temporary Kitchens Ensure Uninterrupted Care:

Confronted with a serious safety issue in their facility, Western Mental Health Institute (WMHI) in Bolivar, TN, urgently needed a rapid solution to maintain foodservice operations while tackling the building’s safety challenges. Partnering with Kitchens To Go (KTG), WMHI quickly transitioned its team to a fully equipped, 53-foot mobile commercial kitchen in June 2022, ensuring continuous meal service for their 150 patients without interruption.

This provisional setup served as a bridge until September 2023, when a modular commercial kitchen solution from KTG was installed that included comprehensive cook, prep, and dishwashing modules plus storage units and seamlessly integrated into WMHI operations. The modular kitchen will support the facility for the next few years while WHMI manages the design, funding, and commissioning of a new facility.

This strategic collaboration not only addressed the critical infrastructure challenge but also led to significant cost savings and operational efficiencies. By avoiding the need for external meal services, WHMI continued to provide high-quality care and support to its patients. The project exemplified adaptability and innovative problem-solving in healthcare, highlighting how rapid response and effective planning can lead to successful long-term solutions in critical service areas.

Additional Case Studies

Connect with us.

Kitchens To Go provides mobile, modular and containerized solutions for projects of any timeframe. Markets and conditions are changing constantly, however, so please connect with us to find out what options are currently available for your project’s need and timeline.

Categories
Case Studies Healthcare

NYU Langone Medical Center

CASE STUDY

NYU Langone Medical Center

When disaster struck the NYU Langone Medical Center, Kitchens To Go provided an interim solution to quickly address the foodservice needs of patients during the aftermath of the storm.

Client

NYU Langone Medical Center

The Need

When Hurricane Sandy struck the northeast in October 2012, NYU Langone Medical Center became one of the many victims of the storm.

The Solution

With no open space, due to constraints in its urban location, the best option was to place an interim containerized kitchen on the roof of a parking garage.

project description

With the rising storm surge and failing back-up generator, the hospital made an important decision and successfully evacuated 322 patients. Once immediate danger was over and the patients were cared for elsewhere, the focus shifted to re-opening the damaged hospital and medical center. After contacting Kitchens To Go in early November for an interim foodservice solution, the first unit arrived and was in place 30 days later.

quick facts
Additional Case Studies
Connect with us.

Kitchens To Go provides mobile, modular and containerized solutions for projects of any timeframe. Markets and conditions are changing constantly, however, so please connect with us to find out what options are currently available for your project’s need and timeline.

Categories
Case Studies Healthcare

Virtua Memorial Hospital

CASE STUDY

Virtua Memorial Hospital

Virtua Memorial needed to maintain foodservice continuity during extended renovations and new construction, and KTG stepped in with a unique modular kitchen complex solution.
Client

Virtua Memorial Hospital is a 433-bed facility in Mt. Holly, NJ, that specializes in Internal Medicine and General Surgeries.

The Need

To provide uninterrupted foodservice to patients, visitors, and staff during the 12 month
renovation and construction.

The Solution

A four unit modular kitchen complex with four cold storage units.

project description

Virtua Memorial reached out to Kitchens To Go for support during a 12-month renovation and construction project that would shut down its kitchen production space. After determining the foodservice capacity necessary to serve all patients, visitors and staff, KTG designed, assembled and installed a four-unit modular kitchen complex in an unutilized space immediately adjacent to the facility, with additional cold units attached to each of the four modules for additional storage. The modular complex fully supported all of Virtua Memorial’s foodservice needs during the entirety of the year-long project, ensuring no interruption of service.

Related Case Studies

Connect with us.

Kitchens To Go provides mobile, modular and containerized solutions for projects of any timeframe. Markets and conditions are changing constantly, however, so please connect with us to find out what options are currently available for your project’s need and timeline.

Categories
Case Studies Healthcare

Banner Thunderbird

CASE STUDY

Banner Thunderbird

A non-profit hospital, Banner Thunderbird Medical Center needed uninterrupted foodservice during renovations. KTG provided a nine-modular complex solution.

Client

Banner Thunderbird Medical Center, a non-profit hospital, is a 513 bed acute-care hospital.

The Need

To provide uninterrupted foodservice to patients, visitors, and staff during a year long renovation. The project included construction of a new 220 bed patient tower, a new main entrance, emergency department, cafeteria and fully remodeled kitchen.

The Solution

An innovative nine unit modular complex with five cold storage units.

project description

Banner Thunderbird Medical Center, is a nonprofit, acute care hospital in Glendale, Arizona, serving the Northwest Valley. Within the nine-modular complex, Kitchens To Go provided two cooking modules with extensive cook lines, a preparation module, two serving modules, a dish-washing module, and three cart employee lock/restroom area.

Additionally, two walk-in coolers and three walk-in freezers were attached to the complex. This modular complex allowed continuous foodservice to the Medical Center during the one-year renovation.